What you must know about Valcros' water purification station

Information meeting for the menbers of the « association syndicat libre» (1), « syndicat du Domaine de Valcros»(2), and «Valcros Rive Droite»(3).
October, 28th, 2006.

The main informations to remenber about the water purification service are the following:

 

• The installation for the water purification has a capacity for 6000 inhabitants (and a potential for 12000), including a network of collecting pipes of

35 Km

. Its purification station treats 70000m3 of dirty water every year.

 

• The whole setting includes a network of collecting pipes, auxiliary pumping stations, a physico chemical purification unit and a biological treatment for refining in the lake “

La Galline

” (this water is kept for watering the golf course).

 

• Some technical transformations are necessary: auto supervision system that conforms to the regulation, (cost: 36500€ in June 2001) and ultraviolet treatment to improve the quality of the pathogenic bacteria rejects (cost: 20000€).

 

• The leasing contract has been denounced by “Domaine de Valcros Ltd” and the “Domaine SDV” on May 16th, 2006, with expiring date on July 1st, 2007. The actual holder of the lease is “VEOLIA” (formerly “CGE”).

 

• The station of purification belongs to “Domaine de Valcros Ltd”. The ASL is in charge of the maintenance of the station and the all network, being its user.

 

• The total cost of water (including distribution and purification) is of 6.29 €/m3. That is to say 115% more compared to the cost of the water treated by the village of

La Londe

, and 337% compared to the purification treatment. The cost of the distribution is the same as for the village. A benefit of 17% added to VEOLIA turnover, plus a VAT of 14.1% (VAT 14.1% = 19.60% (VAT of VEOLIA) – 5.5% (VAT of the district of

La Londe

).are increasing the final price.

 

• The patrimony of the ASL sum up to 5 M€ (not including the assets of the station whose building value was estimated at 1.6 M€ in 1991).

 

• An additional charge has been added to the cost of water since 1994 and has allowed to raise 150000€. However, the communal deposit account planned for special works has a credit of 31000€ in 2006.

 

• The statement of accounts of the year 2005 shows that there are not enough funds to face the renewal of the setting. The subscription of the co-owners of Valcros should be increased from 10 000€ to 150 000€ for several years (150€ per house).

 

• To conclude, the organisation ASL of Valcros has not the human competences required to manage efficiently such important financial issues (network and setting for rain water and purification).

 

• The future of the actual leasing contract:

There are two options, on one side, enter into new negotiation with VEOLIA or advertise for a new bid. On the other side (the most profitable for the users): transfer the maintenance of the installation to the district of La Londe.

Notes:

Note 1: ASL,

Note 2: SDV,

Note 3: VRD